# Crash project duration is obtained by summing the _____ ? with Answer - Civil Engineering Mcqs | TestPrep

> Solved MCQ: Crash project duration is obtained by summing the _____ ? Correct Answer: D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities. Verified answer explanation for FPSC, PPSC, MDCAT, NTS, and CSS competitive exam preparation.

---

Tested in Competitive Exams:

- [NTS Test Prep](https://test-prep.blog/exams/nts)
- [FPSC Past Papers](https://test-prep.blog/exams/fpsc)
- [PPSC Solved MCQs](https://test-prep.blog/exams/ppsc)
- [PMDC MDCAT 2026](https://test-prep.blog/exams/mdcat)
- [UET ECAT Prep](https://test-prep.blog/exams/ecat)
- [CSS Central Superior](https://test-prep.blog/exams/css)

- [Civil Engineering Mcqs](https://test-prep.blog/categories/civil-engineering-mcqs)
Difficulty: Easy 88% Accuracy

# Crash project duration is obtained by summing the _____ ?

Direct Answer & Quick Reference

The correct option is **D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities**.

A. normal durations for all the activities

B. crash durations for all activities

C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities **(Correct Answer)**

Verified Key: D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Solved by 1,718+ students

Verified against official examination board answer keys and standard curriculum textbooks.

- [Previous Question In the lever of third order, load W, effort P and fulcrum F are oriented as follows _____ ?](https://test-prep.blog/mcq/in-the-lever-of-third-order-load-w-effort-p-and-fulcrum-f-are-oriented-as-follow-ca9a19fe-75fd-4d80-8d18-176be69511fb)
- [Next Question The minimum width of the fire escape stairs shall be?](https://test-prep.blog/mcq/the-minimum-width-of-the-fire-escape-stairs-shall-be-ceb3ea95-5f4e-4fb6-8f4d-8ac9e07fe45d)

- [Practice More Civil Engineering Mcqs MCQs](https://test-prep.blog/quiz/smart?category=civil-engineering-mcqs)
- [How We Verify Questions →](https://test-prep.blog/editorial-policy)

## Subject Overview

Explore thousands of solved past paper MCQs for Civil Engineering Mcqs categorized with explanations.

- [Browse All Civil Engineering Mcqs MCQs →](https://test-prep.blog/categories/civil-engineering-mcqs)

## Related Questions

- [In the lever of third order, load W, effort P and fulcrum F are oriented as follows _____ ?](https://test-prep.blog/mcq/in-the-lever-of-third-order-load-w-effort-p-and-fulcrum-f-are-oriented-as-follow-ca9a19fe-75fd-4d80-8d18-176be69511fb)
- [The minimum width of the fire escape stairs shall be?](https://test-prep.blog/mcq/the-minimum-width-of-the-fire-escape-stairs-shall-be-ceb3ea95-5f4e-4fb6-8f4d-8ac9e07fe45d)
- [Choose the wrong statement _____ ?](https://test-prep.blog/mcq/choose-the-wrong-statement-e491e2be-fe10-423a-bc52-050164ea8df3)
- [Choose the wrong statement?](https://test-prep.blog/mcq/choose-the-wrong-statement-ea614ffe-412d-4f02-8d4a-cf59e3d234f6)
- [Choose the wrong statement?](https://test-prep.blog/mcq/choose-the-wrong-statement-fb5efa74-16e8-4f91-a432-96772f86c0ee)

---
*Source: https://test-prep.blog/mcq/crash-project-duration-is-obtained-by-summing-the________________-d0a8b9d5-b033-4285-9d41-fc2f1c05c4ec*
*Format: Markdown for Agents (Content Negotiation: text/markdown)*