# Critical path moves along the activities having total float of _____ ? with Answer - Mechanical Engineering Mcqs | TestPrep

> Solved MCQ: Critical path moves along the activities having total float of _____ ? Correct Answer: C. zero value. Verified answer explanation for FPSC, PPSC, MDCAT, NTS, and CSS competitive exam preparation.

---

Tested in Competitive Exams:

- [NTS Test Prep](https://test-prep.blog/exams/nts)
- [FPSC Past Papers](https://test-prep.blog/exams/fpsc)
- [PPSC Solved MCQs](https://test-prep.blog/exams/ppsc)
- [PMDC MDCAT 2026](https://test-prep.blog/exams/mdcat)
- [UET ECAT Prep](https://test-prep.blog/exams/ecat)
- [CSS Central Superior](https://test-prep.blog/exams/css)

- [Mechanical Engineering Mcqs](https://test-prep.blog/categories/mechanical-engineering-mcqs)
Difficulty: Easy 88% Accuracy

# Critical path moves along the activities having total float of _____ ?

Direct Answer & Quick Reference

The correct option is **C. zero value**.

A. positive value

B. negative value

C. zero value **(Correct Answer)**

D. same value

E. none of the above

✨ Explain with AI

Verified Key: C. zero value
Solved by 2,943+ students

Verified against official examination board answer keys and standard curriculum textbooks.

- [Previous Question The patrol is distilled at a temperature from :](https://test-prep.blog/mcq/the-patrol-is-distilled-at-a-temperature-from-1b1ae628-c41f-4e8c-b36b-585b4f64fa91)
- [Next Question Which of the following are used in diesel engines and oil fired boilers :](https://test-prep.blog/mcq/which-of-the-following-are-used-in-diesel-engines-and-oil-fired-boilers-bc69d84b-a5e7-4469-9ce9-c6b6ca5ebf28)

- [Practice More Mechanical Engineering Mcqs MCQs](https://test-prep.blog/quiz/smart?category=mechanical-engineering-mcqs)
- [How We Verify Questions →](https://test-prep.blog/editorial-policy)

## Subject Overview

Explore thousands of solved past paper MCQs for Mechanical Engineering Mcqs categorized with explanations.

- [Browse All Mechanical Engineering Mcqs MCQs →](https://test-prep.blog/categories/mechanical-engineering-mcqs)

## Related Questions

- [The patrol is distilled at a temperature from :](https://test-prep.blog/mcq/the-patrol-is-distilled-at-a-temperature-from-1b1ae628-c41f-4e8c-b36b-585b4f64fa91)
- [Which of the following are used in diesel engines and oil fired boilers :](https://test-prep.blog/mcq/which-of-the-following-are-used-in-diesel-engines-and-oil-fired-boilers-bc69d84b-a5e7-4469-9ce9-c6b6ca5ebf28)
- [The hydraulic turbines are also known as : _____ ?](https://test-prep.blog/mcq/the-hydraulic-turbines-are-also-known-as-c4281981-41df-4884-900c-0e42a3130767)
- [Which of the following is mostly used used as blast furnace fuel for extracting pig iron from iron ores?](https://test-prep.blog/mcq/which-of-the-following-is-mostly-used-used-as-blast-furnace-fuel-for-extracting--d17a6b4a-fb6a-4d81-9aa0-7d0704d3d22f)
- [Which of the following solid fuel has high carbon content?](https://test-prep.blog/mcq/which-of-the-following-solid-fuel-has-high-carbon-content-23ab9cf2-4a63-4460-9aa4-9651149f7b7e)

---
*Source: https://test-prep.blog/mcq/critical-path-moves-along-the-activities-having-total-float-of-af7cac8a-750a-477c-9b43-2fa99f0a3eb4*
*Format: Markdown for Agents (Content Negotiation: text/markdown)*
