# In the critical path method of construction planning, Free Float can be _____ ? with Answer - Civil Engineering Mcqs | TestPrep

> Solved MCQ: In the critical path method of construction planning, Free Float can be _____ ? Correct Answer: 1. greater than Total Float.2. greater than Independent Float3. equal to Total Float.4. less than Independent Float. Of these statements. Verified answer explanation for FPSC, PPSC, MDCAT, NTS, and CSS competitive exam preparation.

---

Tested in Competitive Exams:

- [NTS Test Prep](https://test-prep.blog/exams/nts)
- [FPSC Past Papers](https://test-prep.blog/exams/fpsc)
- [PPSC Solved MCQs](https://test-prep.blog/exams/ppsc)
- [PMDC MDCAT 2026](https://test-prep.blog/exams/mdcat)
- [UET ECAT Prep](https://test-prep.blog/exams/ecat)
- [CSS Central Superior](https://test-prep.blog/exams/css)

- [Civil Engineering Mcqs](https://test-prep.blog/categories/civil-engineering-mcqs)
Difficulty: Easy 79% Accuracy

# In the critical path method of construction planning, Free Float can be _____ ?

Direct Answer & Quick Reference

The correct option is **1. greater than Total Float.2. greater than Independent Float3. equal to Total Float.4. less than Independent Float. Of these statements**.

A. 1 and 4 are correct

B. 2 and 3 are correct

C. 1 and 4 are correct

D. 1 and 2 are correct

✨ Explain with AI

Verified Key: 1. greater than Total Float.2. greater than Independent Float3. equal to Total Float.4. less than Independent Float. Of these statements
Solved by 3,599+ students

Verified against official examination board answer keys and standard curriculum textbooks.

- [Previous Question In the lever of third order, load W, effort P and fulcrum F are oriented as follows _____ ?](https://test-prep.blog/mcq/in-the-lever-of-third-order-load-w-effort-p-and-fulcrum-f-are-oriented-as-follow-ca9a19fe-75fd-4d80-8d18-176be69511fb)
- [Next Question The minimum width of the fire escape stairs shall be?](https://test-prep.blog/mcq/the-minimum-width-of-the-fire-escape-stairs-shall-be-ceb3ea95-5f4e-4fb6-8f4d-8ac9e07fe45d)

- [Practice More Civil Engineering Mcqs MCQs](https://test-prep.blog/quiz/smart?category=civil-engineering-mcqs)
- [How We Verify Questions →](https://test-prep.blog/editorial-policy)

## Subject Overview

Explore thousands of solved past paper MCQs for Civil Engineering Mcqs categorized with explanations.

- [Browse All Civil Engineering Mcqs MCQs →](https://test-prep.blog/categories/civil-engineering-mcqs)

## Related Questions

- [In the lever of third order, load W, effort P and fulcrum F are oriented as follows _____ ?](https://test-prep.blog/mcq/in-the-lever-of-third-order-load-w-effort-p-and-fulcrum-f-are-oriented-as-follow-ca9a19fe-75fd-4d80-8d18-176be69511fb)
- [The minimum width of the fire escape stairs shall be?](https://test-prep.blog/mcq/the-minimum-width-of-the-fire-escape-stairs-shall-be-ceb3ea95-5f4e-4fb6-8f4d-8ac9e07fe45d)
- [Choose the wrong statement _____ ?](https://test-prep.blog/mcq/choose-the-wrong-statement-e491e2be-fe10-423a-bc52-050164ea8df3)
- [Choose the wrong statement?](https://test-prep.blog/mcq/choose-the-wrong-statement-ea614ffe-412d-4f02-8d4a-cf59e3d234f6)
- [Choose the wrong statement?](https://test-prep.blog/mcq/choose-the-wrong-statement-fb5efa74-16e8-4f91-a432-96772f86c0ee)

---
*Source: https://test-prep.blog/mcq/in-the-critical-path-method-of-construction-planning-free-float-can-be__________-7ff34d47-00dd-4941-8823-99b746aeda11*
*Format: Markdown for Agents (Content Negotiation: text/markdown)*